Press
Release
DATE: March 27, 2008
DESIRED
PUBLICATION DATE: Friday, March 28, 2008
SUBJECT: State Route 95 (Oak Ridge Turnpike) from near Westover Drive to
State Route 62 (Illinois Avenue)
Beginning
the week of March 31, 2008, construction will begin on roadway widening
improvements along State Route 95 (Oak Ridge Turnpike) from near Westover Drive
to State Route 62 (Illinois Avenue).
Initially work will include the installation of construction signs and
clearing of the right-of-way area outside of the traffic lanes. Some initial utility work will begin within
a few weeks. Tentatively within the
next one to two months, the four-lane roadway will be reduced to two traffic
lanes (one lane in each direction) for construction of the roadway widening on
the north side of the Turnpike. Within
the next year, the two traffic lanes will be moved to the opposite side for
widening of the Turnpike on the south side.
The expected completion date of this 4.2-mile roadway section is July
2010.
This
approximate $26 million project requires significant utility and roadway
construction and some work will occur at night to complete the project within
the required completion time. At times,
there will be temporary traffic lane and side street closures. Through Press Releases, the City will make
every effort possible to advise motorist of the closures. Motorists should
exercise caution during this lengthy construction period within the
construction zone.
You
may contact the City Engineer @ 425-1807 for additional information on the
roadway project.